Convection Section Replacement

View All Projects

Project Overview

The Client engaged Rally to replace the entire convection section of the heater, including the stack.

Budget:
$7.8M TIC
Category:
Refining & Petrochemicals
Location:
Alberta
Download PDF

SCOPE OF WORK

Rally worked to optimize the design of a new convection section and stack.  The goal was to improve duty and draft whilst still integrating seamlessly with the radiant sections below. Rally modularized the steam drum piping and access platform so that they could be trial fit on top of the new convection section prior to lifting.  All new equipment was designed to meet modern codes and standards, including the multi-blade damper and steam drum.

DELIVERABLES

Material requisitions (MRs) were issued for the new convection section and stack, the steam drum and module, pressure relief valves, modern oxygen analyzers, and other instruments. Construction work packages (CWPs) were produced to reinforce the existing radiant sections, lift and remove the old convection section, execute the lifts of the new convection section, stack, and steam drum module, tie into adjacent piping and wiring, and upgrade instruments.  

Let's Get Started

Build With Rally Today

Ready to work with the leading provider of engineering, procurement, and construction management services? Join Canada’s largest infrastructure-building companies, and partner with Rally today!

Our Work

View Our Projects

View More Work