Rally provided detailed engineering design of piping, piping stress, and floor penetration requirements for a new vessel. Rally reviewed the new vessel weight and potential support from the floor in combination with the vessel below.
• Assisted the Client with design to raise the vessel 8 ft. for tie-in accommodations.
• Completed stress analysis on new piping and tie-in locations.
• Completed calculations, provided CWP with a drawing to complete the new floor penetration for the new exchanger vessel.
• Designed spring supports for the cooling water lines.
• Completed 3D model (exchanger and relevant piping) for the purposes of generating isometric drawings.