Flare Tip Replacement

View All Projects

Project Overview

Budget:
$3.5M TIC
Category:
Refining & Petrochemicals
Location:
Saskatchewan
Download PDF

Procurement Support

Prior to turnaround, the new flare tip was 3D laser scanned at grade and the existing flare tip was scanned from a helicopter. This allowed Rally to cross-check the measurements, ensuring that the new flare tip would integrate seamlessly with the existing stack. Rally also procured a new steam control valve, orifice plates, and various flow, pressure, and temperature instruments.

Construction Activities

Rally produced construction work packages (CWPs) for the mechanical, piping, electrical, and instrumentation field work. The packages detailed how to demolish the existing flare tip, install the new tip, revamp the piping, electrically heat trace the drain system, install new instruments, and connect to the new flame front generator control panel.

Rally personnel were on-site to support the turnaround work. All construction activities were executed as per the schedule, with no fit-up issues.

Let's Get Started

Build With Rally Today

Ready to work with the leading provider of engineering, procurement, and construction management services? Join Canada’s largest infrastructure-building companies, and partner with Rally today!

Our Work

View Our Projects

View More Work