Granulation Dissolver Tank Repairs

View All Projects

Project Overview

Budget:
$500k TIC
Category:
Mining & Metals
Location:
Alberta
Download PDF

Scope of Work

Structural and mechanical engineering services in support of the pedestal reconstruction work. Rally also became engaged in the planning of all aspects of the fast-tracked engineering, procurement, and construction management.

Deliverables

Construction work package (CWP) with detailed instructions for the following:

• Installation of a temporary support structure to allow demolition of the dissolver tank pedestal.

• Installation of a stainless structural steel space frame to replace the original concrete pedestal.

• Installation of a concrete slab to restore the floor.

To minimize the impact to ongoing operations, the tank foundation reconstruction work was planned for and executed during a regular seven-day plant maintenance outage. The work was completed ahead of schedule and at a cost below the AFE estimate.