The goal was to install a new pump that would mitigate the safety & reliability risks associated with a single seal failure, while also increasing capacity by 50%. The project team elected to purchase an API 685 seal-less (canned motor) pump, using engineering design to eliminate the possibility of seal failure. The team also repurposed an abandoned pump foundation, saving the project money and allowing the new pump to be installed off-line.
Rally produced the material requisition (MR) for two new seal-less pumps – one for installation, and one for a warehouse spare. In the unlikely event of a pump breakdown, the unitized pump and motor assembly can be changed out in one 8-hour shift.
Rally also procured new instrumentation including a flow meter, a flow control valve, pressure safety valves, motor operated valves, and various gauges and transmitters.
The piping tie-ins, electrical and instrumentation terminations, and new pump commissioning all took place in a 6 day outage.
Ready to work with the leading provider of engineering, procurement, and construction management services? Join Canada’s largest infrastructure-building companies, and partner with Rally today!